The development of foreign economic relations and oil industries episode {61}

Go down

The development of foreign economic relations and oil industries episode {61} Empty The development of foreign economic relations and oil industries episode {61}

Post  Admin Sun Mar 06, 2016 8:07 am

3/6/2016 0:00

The Ministry of Commerce on the priority development of foreign economic relations with the countries of the world through two programs:


● The percentage of achievement in the development of foreign economic relations with the countries of the world program (44 percent), an annual program, which includes (6) activities, including the signing of agreements and open attache offices, the signing of memorandums of understanding for joint committees, attending meetings and Orcha external and internal courses. Cost (2.579) billion, and by the amount of progress (27 percent) than it was at the beginning of this year.


● As for Bernameh create a favorable environment for private sector development and the development of investment is the establishment of international trade point, it is implemented through a single project at a cost of $ (1.074) billion completion rate and which was (25 percent have not changed) than it was in 2014 because of not to launch customizations.


• activating the role of state banks and specialized banks and private banks (civil) to provide soft loans to the private sector and the national as well as finding solutions to the problems of taxes and accrued interest resulting from the stalled project for the owners of production solutions.


● gave the Central Bank (CBI loan program for the year 2015). Financial ceiling of $ 5 trillion.


● acknowledged the crisis cell at its sixth meeting on 08.24.2015 under the chairmanship of Prime Minister and lending mechanism in the industrial, agricultural and housing area, through this program.


● Central Bank issued instructions that will be given loans, according to them from the central bank and other banks.


● The Bank is examining the possibility of granting facilities for private banks to micro-finance, small and medium.


● Bank will work on the restructuring of state-owned banks and other specialized banks.
● With regard to the second part of the priority (to find solutions to the problems of taxes and accrued interest resulting from the owners of the stalled projects for production) it offered nothing so far.


● develop mechanisms and conditions for the distribution of the Central Bank for banks and specialized housing fund loan and submit it to the General Secretariat of the Council of Ministers and the distribution of funds between banks and housing fund, according to the distribution of the Committee on Economic Affairs and the Central Bank of Iraq and classified loans for projects of specialized banks in accordance with the following:


1. Small projects limit higher (500 million dinars).


2. Medium Enterprises upper limit (two billion dinars).


3. large projects has increased to about (two billion dinars), provided that does not exceed the upper limit (20 billion dinars).


 With regard to finding solutions to the problems of accumulated tax benefits resulting from the stalled project for the owners of production solutions, it was the Ministry of Finance measures as follows:


● it has been completed 85 percent of the business restructuring and will be applied to all decisions of the Supreme Supervisory Committee to restructure the Rafidain Bank until 2015 to complete the restructuring will be 100 percent in the years (2016-2017).


● For the benefits of the Rafidain Bank can not exempt the accumulated interest, to the adoption of financing loans class basis on the money of depositors citizens with the bank and the bank pays them annual interest of not less than 6 percent.


● The adoption of a mechanism in the Industrial Bank to reschedule loan balance with the benefits obstructed and stalled for repayment new mechanism within the extended benefits is that the granting of loans and facilities on this basis in order to collect those loans and give flexibility to the customers in repayment and profitability of the bank and the lifting of the state of recession that passed by.


● Rafidain Bank began granting self-financing circles loans to pay salaries owed to employees circles above for the year 2010 and exceeded the credit limit granted by the Central Bank of Iraq to the bank over the years 2010 to 2013 and in 2014 has increased credit limit to 10 trillion, while in the year 2015 has increased credit limit granted to (11) Trliuna Ministry has to pay the sum of (1900) billion dinars to extinguish loans granted in previous years and to consider the loans granted by the bank during 2015, our ministry, while the loans granted to the private investment sector, which is among the stalled for production projects, amounting to (25,079) billion dinars and that the benefits of it at $ 1600 billion dinars.


• emphasis on the application of the laws relating to the protection of all the local product as well as consumer and procedures for quality control of imported materials and goods protection.


The work of the Central Organization for Standardization and Quality Control on the rehabilitation of testing laboratories to improve the quality of device services to the international level, where the number of qualified laboratories (5) laboratory and by an increase of 25 percent from what it was in 2014 for consumer and procedures of quality control on imported materials and goods protection.


Axis IV: increased oil and gas production to improve the financial sustainability
This included the axis (5) priorities, worked the oil ministry on implementation.




The most important achievements in this axis are as follows:


• Increase energies Alkhoznip oil and gas.


● reached Alkhoznip capacity of crude oil for the year 2015 (14,500 barrels), an increase of 3,250 barrels from what it was in 2014, as it was for 2014 (11,250 barrels).


● reached the proportion of the annual completion of projects increased Alkhoznip energy rate up to 09.30.2015 (46 percent) and an increase of $ (24 percent), as implemented this priority through three programs, the first storage system and pumping and transportation of crude oil and gas / SOC, and the second expand crude oil depot in Faw / Enterprise Co., and the third qualifying warehouse storage and pumping crude oil / project company.


● completion of tanks number (4) with a capacity of 66,000 cubic meters each tank in the brick warehouse was introduced to work.


● completion of an oil tank raw number (1) with a capacity of 82,000 cubic meters per PS1 warehouse was admitted to work.


● completion of reservoirs (2) with a capacity of 58,000 cubic meters each tank in Zubayr, warehouse / 1 was introduced to work.


● completion of tanks number (3) with a capacity of 58,000 cubic meters each tank at the FAO warehouse was introduced to work.


• Increased oil and gas production and improve quality specifications
The exploitation of associated gas and reduce quantities of it scorched


● complete the NGL plant card 110 Mqmq Sepah in the field of investment associated gas and reduce the quantities scorched him.


● complete the project pipeline Sweet 24 knots (Majnoon -mahth North Rumaila electricity), except for acts of cathodic protection of the pipeline.


● completion of dry gas pipeline 24 feeder station Diwaniyah electricity knots.


● completion of pipeline fuel oil (accelerated) to feed the Shatt al-Basra power plant fuel oil from the Basra refinery 9.5 km long.


● averaged annual rate of completion of projects, the exploitation of associated gas and reduce quantities of it burned up to 09.30.2015 (62 percent) and implement this priority through 19 projects to build gas pipelines and set up pumping stations and increase energy Alkhoznip gas.


• construction of new refineries in the cities of Karbala and Missan and Nasiriyah.


● annual rate of achievement for projects to increase crude oil refining operations to provide petroleum products up to 09.30.2015 (37 percent) and implement this priority through 28 projects.


● complete the creation of the mobilization of Samawa gas station and bottling plant granular gas.


● completion of liquid gas spherical tanks in Taji, Hilla, Rusafa, Diwaniya, the rate of one tank with a capacity of 3,000 cubic meters each site.


● complete the project and the third unit to improve gasoline in the Basra refinery 10,000 barrels per day.


● sign a contract with the company TECHNO EXPORT Algikip to add refining unit in the Basra refinery 70,000 barrels per day card to become a total energy refined 280,000 barrels per day.


● increase in the production of oil derivatives produced rates and improve quality through the isomerization unit in the refinery project and two hydrogenation of naphtha and improve gasoline refinery in Samawa.




● projects to set up new refineries:


1. refinery in Karbala card 140 000 barrels per day and work is continuing acts of the EPC.


2. Missan refinery capacity of 150 thousand barrels per day and the investing company has signed a lease contract and processing of crude oil and refined processing of water.


3. Nasiriyah refinery capacity of 300 thousand barrels per day under Advertising and assignment.


4. refinery in Kirkuk, 150 thousand barrels per day card at the stage of receiving offers and studied.



• expand exploration of oil and gas reserves.



● completion of the fourth round of licenses for exploratory patches (12,10,9,Cool in the provinces (Diyala / Wasit, Basra, Muthanna and / Dhi Qar, Najaf and / Muthanna) and to companies (pakistan Petroleum) within the area of ​​eight, and the companies (Kuwait Energy, Dragon United Arab Emirates, and the Egyptian Petroleum Authority) within the area of ​​nine, and to companies (Lukoil Russian and Japanese Inpex) within the area of ​​the tenth, and to companies (Premier of British and Russian Bashneft) within twelve board.



● averaged annual rate of completion of expansion projects in the field of exploration and drilling capacity gas and oil wells (55 percent) and by the amount offered (33 percent) than it was at the beginning of 2014, since it is the annual projects. And implemented through two projects, where the percentage of completion of the project first: the rehabilitation and purchase seismic teams and laboratory environmental Mobile (55 percent) and the second project: update and technical support for systems operating in the company and the purchase of hardware and software (56 percent).



• Increased export capacity and expand its outlets.



• implement a priority to increase the export capacity and expand its outlets through two programs, the first program, the development of the export system, and the second program is the development of the national effort fields and upgrading operations drilling of oil wells to increase production.

Develop export system

● crude oil export rate for the period (1.9.2014 until 09.30.2015) 2 862 thousand barrels per day.



● completion of the crude oil pipeline (Zubair 1 - FAO) 50 km.



● completion of the strategic crude oil pipeline (Bozrah - PS3) a length of 225 km.



● annual completion of projects to develop system software export rate up to 30.9.2015 was (88.53 percent) and implemented through 13 projects.



• Develop a national effort and upgrading operations drilling of oil wells to increase production fields


● Crude oil production rate (licensing rounds fields and fields of the national effort) for the period
(01.09.2014 till 09.30.2015) 3236 thousand barrels per day.


● annual delivery rate of development projects and upgrading the national effort to excavate Alabaralnaftyh up to 30.9.2015 fields (63 percent) and implement this priority through 22 projects.


http://www.alsabaah.iq/ArticleShow.aspx?ID=111811

Admin
Admin

Posts : 29357
Join date : 2012-04-30
Location : Arizona

https://iraqidinar.forumotion.com

Back to top Go down

Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum